• Welcome to CableDataSheet, Cable and Wire Technical Consulting Service.
 

News:

You are not allowed to view links. Register or Login
You are not allowed to view links. Register or Login
You are not allowed to view links. Register or Login
You are not allowed to view links. Register or Login
Tacettin İKİZ



Main Menu

EHV/HV Underground Cable Sheath Earthing

Started by cabledatasheet, July 09, 2013, 11:21:00 AM

Previous topic - Next topic

cabledatasheet



EHV/HV Underground Cable Sheath Earthing

In urban areas, high voltage underground cables are commonly used for the transmission and distribution of electricity. Such high voltage cables have metallic sheaths or screens surrounding the conductors, and/or armour and metallic wires surrounding the cables.

During earth faults applied to directly earthed systems, these metallic paths are expected to carry a substantial proportion of the total fault current, which would otherwise flow through the general mass of earth, while returning to system neutrals. These alternative return paths must be considered when determining the extent of the grid potential rise at an electrical plant due to earth faults.

For safety and reliable operation, the shields and metallic sheaths of power cables must be grounded. Without grounding, shields would operate at a potential considerably above ground. Thus, they would be hazardous to touch and would cause rapid degradation of the jacket or other material intervening between shield and ground. This is caused by the capacitive charging current of the cable insulation that is on the order of 1 mA/ft of conductor length.

This current normally flows, at power frequency, between the conductor and the earth electrode of the cable, normally the shield. In addition, the shield or metallic sheath provides a fault return path in the event of insulation failure, permitting rapid operation of the protection devices.

In order to reduce circulating current and electric potential difference between the sheathings of single core three-phase cables, the sheathing is grounded and bonded at one or both ends of the cables. If the cable is long, double bonding has to be carried out which leads to circulating currents and increased total power loss. Raising the sheath's resistance, by decreasing its cross section and increasing its resistivity, can reduce this almost to the level of the core losses.

However, in case of an earth fault, a considerable portion of the fault current flows through the increased sheath resistance, creating much higher power in the sheaths than in the faulty core. A simple solution, a conductor rod buried into the soil above or under the cable can divert this power from the sheaths.


Cable Screen
1. Purpose of cable screen




Cable screen controls the electric field stress in the cable insulation. It also provides return path for cable neutral and fault current.

If the screen is earthed at two ends than it provides shielding for electromagnetic radiation. Enclosing dangerous high voltage with earth potential for safety.

2. Purpose of bonding cable screens at both ends

The electric power losses in a cable circuit are dependent on the currents flowing in the metallic sheaths of the cables so by reducing the current flows in metallic sheath by different methods of bonding we can increases the load current carrying capacity (ampacity) of the cable.

It provides low impedance fault current return path and provides neutral point for the circuit. It also provides shielding of electromagnetic field.

3. Induced voltage & circulating circulating current in cable screen

Electromagnetic coupling between the core and screen Electromagnetic screen. If the cable screen is single point bonded, no electrical continuity and mmf generates a voltage. If the cable screen is bonded at both ends, the mmf will cause circulating current to flow if there is electrical continuity.

The circulating current produces an opposing magnetic field. Suitable bonding method should be employed to meet the standing voltage limit and keep circulating current to an acceptable level.

TopLaying Method Of Cable

The three Single core cables in a 3-phase circuit can be placed in different formations. Typical formations include trefoil (triangular) and flat formations.

1. Trefoil Formation


To minimize the electromechanical forces between the cables under short-circuit conditions, and to avoid eddy-current heating in nearby steelwork due to magnetic fields set up by load currents, the three single-core cables comprising the three phases of a 3-phase circuit are always run clamped in 'Trefoil' formation.

Advantages

This type of Formation minimizes the sheath circulating currents induced by the magnetic flux linking the cable conductors and metallic sheath or copper wire screens. This configuration is generally used for cables of lower voltages (33 to 132kV) and of smaller conductor sizes.

Disadvantages

The trefoil formation is not appropriate for heat dissipation because there is an appreciable mutual heating effect of the three cables. The cumulated heat in cables and cable trench has the effect of reducing the cable rating and accelerating the cable ageing.

2. Flat Formation



    This is a most common method for Laying LT Cable.
    This formation is appropriate for heat dissipation and to increase cable rating.
    The Formation choice is totally deepened on several factors like screen bonding method, conductor area and available space for installation.

TopType of Core and Induced Voltage

1. Three Core Cable

    For LT application, typically for below 11 kV.
    Well balanced magnetic field from Three Phase.
    Induced voltages from three phases sum to zero along the entire length of the cable.
    Cable screen should be earthed at both ends
    Virtually zero induced voltage or circulating current under steady state operation.

2. Single Core Cable

    For HV application, typically for 11 kV and above.
    Single–core cables neglects the use of ferromagnetic material for screen, sheath and armoring.
    Induced voltage is mainly contributed by the core currents in its own phase and other two phases.If cables are laid in a compact and symmetrical formation, induced in the screen can be minimized.
    A suitable screen bonding method should be used for single–core cables to prevent Excessive circulating current, high induced standing voltage.igh voltage.

References

    Mitton Consulting.
    EMElectricals


cabledatasheet

Accessories for HT Cable Sheath Bonding
1. Function of Link Box?




Link Box is electrically and mechanically one of the integral accessories of HV underground above ground cable bonding system, associated with HV XLPE power cable systems. Link boxes are used with cable joints and terminations to provide easy access to shield breaks for test purposes and to limit voltage build-up on the sheath.

Lightning, fault currents and switching operations can cause over voltages on the cable sheath. The link box optimizes loss management in the cable shield on cables grounded both sides. In HT Cable the bonding system is so designed that the cable sheaths are bonded and earthed or with SVL in such way as to eliminate or reduce the circulating sheath currents.

Link Boxes are used with cable joints and terminations to provide easy access to shield breaks for test purposes and to limit voltage build-up on the sheath. The link box is part of bonding system, which is essential of improving current carrying capacity and human protection.


2. Sheath Voltage Limiters (SVL) (Surge Arrestors)


SVL is protective device to limit induce voltages appearing on the bonded cable system due to short circuit.

It is necessary to fit SVL's between the metallic screen and ground inside the link box. The screen separation of power cable joint (insulated joint) will be protected against possible damages as a result of induced voltages caused by short circuit/break down.

Top Type of Sheath Bonding for HT Cable

There is normally three type of bonding for LT/HT cable screen:

    Single Point Bonded
    One Side Single Point Bonded System.
    Split Single Point Bonded System.
    Both End Bonded System
    Cross Bonded System

1. Single point bonded system
1a. One Side Single Bonded System



    A system is single point bonded if the arrangements are such that the cable sheaths provide no path for the flow of circulating currents or external fault currents.
    This is the simplest form of special bonding. The sheaths of the three cable sections are connected and grounded at one point only along their length. At all other points there will be a voltage between sheath and ground and between screens of adjacent phases of the cable circuit that will be at its maximum at the farthest point from the ground bond.
    This induced voltage is proportional to the cable length and current. Single-point bonding can only be used for limited route lengths, but in general the accepted screen voltage potential limits the length
    The sheaths must therefore be adequately insulated from ground. Since there is no closed sheath circuit, except through the sheath voltage limiter, current does not normally flow longitudinally along the sheaths and no sheath circulation current loss occurs.
    Open circuit in cable screen, no circulating current.
    Zero volt at the earthed end, standing voltage at the unearthed end.
    Optional PVC insulated earth continuity conductor required to provide path for fault current, if returning from earth is undesirable, such as in a coal mine.
    SVL installed at the unearthed end to protect the cable insulation during fault conditions.
    Induced voltage proportional to the length of the cable and the current carried in the cable .
    Zero volt with respect to the earth grid voltage at the earthed end, standing voltage at the unearthed end.
    Circulating current in the earth–continuity conductor is not significant, as magnetic fields from phases are partially balanced.
    The magnitude of the standing voltage is depended on the magnitude of the current flows in the core, much higher if there is an earth fault.
    High voltage appears on the unearthed end can cause arcing and damage outer PVC sheath.
    The voltage on the screen during a fault also depends on the earthing condition.

Standing voltage at the unearthed end during earth fault condition:


    During a ground fault on the power system the zero sequence current carried by the cable conductors could return by whatever external paths are available. A ground fault in the immediate vicinity of the cable can cause a large difference in ground potential rise between the two ends of the cable system, posing hazards to personnel and equipment.
    For this reason, single-point bonded cable installations need a parallel ground conductor, grounded at both ends of the cable route and installed very close to the cable conductors, to carry the fault current during ground faults and to limit the voltage rise of the sheath during ground faults to an acceptable level.
    The parallel ground continuity conductor is usually insulated to avoid corrosion and transposed, if the cables are not transposed, to avoid circulating currents and losses during normal operating conditions.
    Voltage at the unearthed end during an earth fault consists of two voltage components. Induced voltage due to fault current in the core.


Advantages


    No circulating current.
    No heating in the cable screen.
    Economical.

Disadvantages

    Standing voltage at the un–earthed end.
    Requires SVL if standing voltage during fault is excessive.
    Requires additional earth continuity conductor for fault current if earth returned current is undesirable. Higher magnetic fields around the cable compared to solidly bonded system.

    Standing voltage on the cable screen is proportional to the length of the cable and the magnitude of current in the core.
    Typically suitable for cable sections less than 500 m, or one drum length.


1b. Split Single Point-bonded System




    It is also known as double length single point bonding System.
    Cable screen continuity is interrupted at the midpoint and SVLs need to be fitted at each side of the isolation joint.
    Other requirements are identical to single–point–bonding system like SVL, Earth continuity Conductor, Transposition of earth continuity conductor.
    Effectively two sections of single–point–bonding.
    No circulating current and Zero volt at the earthed ends, standing voltage at the sectionalizing joint.

Advantages

    No circulating current in the screen.
    No heating effect in the cable screen.
    Suitable for longer cable section compared to single–point–bonding system and solidly bonded single-core system.
    Economical.

Disadvantages


    Standing voltage exists at the screen and sectionalizing insulation joint.
    Requires SVL to protect the un–earthed end.
    Requires separate earth continuity conductor for zero sequence current.
    Not suitable for cable sections over 1000 m.
    Suitable for 300~1000 m long cable sections, double the length of single–point–bonding system.

2. Both End Solidly Bonded (Single-core cable) systems



    Most Simple and Common method.
    Cable screen is bonded to earth grids at both ends (via link box).
    To eliminate the induced voltages in Cable Screen is to bond (Earth) the sheath at both ends of the cable circuit.
    This eliminates the need for the parallel continuity conductor used in single bonding systems. It also eliminates the need to provide SVL, such as that used at the free end of single-point bonding cable circuits
    Significant circulating current in the screen Proportional to the core current and cable length and de rates cable.
    Could lay cable in compact trefoil formation if permissible.
    Suitable for route length of more than 500 Meter.
    Very small standing voltage in the order of several volts.

Advantages

    Minimum material required.
    Most economical if heating is not a main issue.
    Provides path for fault current, minimizing earth return current and EGVR at cable destination.
    Does not require screen voltage limiter (SVL).
    Less electromagnetic radiation.

Disadvantages


    Provides path for circulating current.
    Heating effects in cable screen, greater losses .Cable therefore might need to be de–rated or larger cable required.
    Transfers voltages between sites when there is an EGVR at one site.
    Can lay cables in trefoil formation to reduce screen losses .
    Normally applies to short cable section of tens of meters long. Circulating current is proportional to the length of the cable and the magnitude of the load current.

3. Cross-bonded cable system




    A system is cross-bonded if the arrangements are such that the circuit provides electrically continuous sheath runs from earthed termination to earthed termination but with the sheaths so sectionalized and cross-connected in order to reduce the sheath circulating currents.
    In This Type voltage will be induced between screen and earth, but no significant current will flow.
    The maximum induced voltage will appear at the link boxes for cross-bonding. This method permits a cable current-carrying capacity as high as with single-point bonding but longer route lengths than the latter. It requires screen separation and additional link boxes.
    For cross bonding, the cable length is divided into three approximately equal sections. Each of the three alternating magnetic fields induces a voltage with a phase shift of 120° in the cable shields.
    The cross bonding takes place in the link boxes. Ideally, the vectorial addition of the induced voltages results in U (Rise) = 0. In practice, the cable length and the laying conditions will vary, resulting in a small residual voltage and a negligible current. Since there is no current flow, there are practically no losses in the screen.
    The total of the three voltages is zero, thus the ends of the three sections can be grounded.
    Summing up induced voltage in sectionalized screen from each phase resulting in neutralization of induced voltages in three consecutive minor sections.
    Normally one drum length (500 m approx) per minor section.
    Sectionalizing position and cable jointing position should be coincident.
    Solidly earthed at major section joints.
    Transpose cable core to balance the magnitude of induced voltages to be summed up.
    Link box should be used at every sectionalizing joint and balanced impedance in all phases.
    Induced voltage magnitude profile along the screen of a major section in the cross–bonding cable system.
    Virtually zero circulating current and Voltage to the remote earth at the solidly earthed ends.
    In order to obtain optimal result, two ''crosses'' exist. One is Transposition of cable core crossing cable core at each section and second is Cross bond the cable screens effectively no transposition of screen.
    Cross bonding of cable screen: It is cancelled induced voltage in the screen at every major Section joint.
    Transposition of cables: It is ensure voltages to be summed up have similar magnitude .Greater standing voltage at the screen of the outer cable.
    Standing voltages exist at screen and majority of section joints cable and joints must be installed as an insulated screen system.

Requirement of transpose for cables core




    If core not transposed, not well neutralized resulting in some circulating currents.
    Cable should be transposed and the screen needs to be cross bonded at each sectionalizing joint position for optimal neutralization

Advantages

    Not required any earth continuity conductor.
    Virtually zero circulating current in the screen.
    Standing voltage in the screen is controlled.
    Technically superior than other methods.
    Suitable for long distance cable network.

Disadvantages


    Technically complicated.
    More expensive.

Sheath Losses according to type of Bonding

    Sheath losses are current-dependent losses and are generated by the induced currents when load current flows in cable conductors.
    The sheath currents in single-core cables are induced by "transformer" effect; You are not allowed to view links. Register or Login the magnetic field of alternating current flowing in cable conductor which induces voltages in cable sheath or other parallel conductors.
    The sheath induced electromotive forces (EMF) generate two types of losses: circulating current losses (Y1) and eddy current losses (Y2), so the total losses in cable metallic sheath are: Y= Y1+Y2
    The eddy currents circulating radially and longitudinally of cable sheaths are generated on similar principles of skin and proximity effects i.e. they are induced by the conductor currents, sheath circulating currents and by currents circulating in close proximity current carrying conductors.
    They are generated in cable sheath irrespective of bonding system of single core cables or of three-core cables
    The eddy currents are generally of smaller magnitude when comparing with circuit (circulating) currents of solidly bonded cable sheaths and may be neglects except in the case of large segmental conductors and are calculated in accordance with formulae given in the IEC60287.
    Circulating currents are generated in cable sheath if the sheaths form a closed loop when bonded together at the remote ends or intermediate points along the cable route.
    These losses are named sheath circulating current losses and they are determined by the magnitude of current in cable conductor, frequency, mean diameter, the resistance of cable sheath and the distance between single-core cables.

Conclusion

There is much disagreement as to whether the cable shield should be grounded at both ends or at only one end. If grounded at only one end, any possible fault current must traverse the length from the fault to the grounded end, imposing high current on the usually very light shield conductor. Such a current could readily damage or destroy the shield and require replacement of the entire cable rather than only the faulted section.

With both ends grounded, the fault current would divide and flow to both ends, reducing the duty on the shield, with consequently less chance of damage.

Multiple grounding, rather than just grounding at both ends, is simply the grounding of the cable shield or sheath at all access points, such as manholes or pull boxes. This also limits possible shield damage to only the faulted section.

References

    Mitton Consulting.
    EMElectricals

Document echo ' ';