Construction of the Newest Extra High Voltage Plant in North America has Reached

Started by cabledatasheet, May 17, 2013, 11:06:03 PM

Previous topic - Next topic

cabledatasheet



Construction of the Newest Extra High Voltage Plant in North America has Reached a Pivotal Stage

The construction of a 409 foot (125 m) tower for the Nexans Extra High Voltage plant in South Carolina is now complete.

Construction of the vertical continuous vulcanization (VCV) tower, which will house the triple extrusion process, began on Monday, January 7th.  This was a non-stop 24/7 operation for 20 days.  Each hour, three trucks delivered 8,000 cubic yards (6,000 m3) of concrete for the slip pour.

The Tower is the hub of the extrusion process and pivotal for the entire operation.  This milestone is the first step towards the completion of our state of the art operation by 2014.

"The commitment of $85 million toward the construction of our newest extra high voltage plant in South Carolina demonstrates Nexans' position in the fast growing North American market," Fréderic Michelland, Senior Corporate Executive Vice President, High-Voltage and Underwater Cables Business Group, and North America and South America Areas.